Construction Change Directive definition

Construction Change Directive means a written order prepared by Owner Parties and signed by Owner directing Contractor to perform a change in the Work prior to agreeing to a change, if any, to the Contract Time, schedule of performance of the Work, Contract Sum, or Contractor’s compensation.
Construction Change Directive means an approved change in the Work issued by the Owner without the complete agreement of Contractor as to cost and/or time.
Construction Change Directive means a written order directed to the Contractor and signed by the Owner, directing a change in the Work and stating a proposed basis for adjustment, if any, in the Contract Sum or Contract Time, or both, as defined more fully in paragraphs 7.3.1-7.3.9.

Examples of Construction Change Directive in a sentence

  • Any dispute as to the adjustment of the Guaranteed Maximum Price, if any, of the Construction Change Directive or timing of payment shall be resolved pursuant to the Payment and Claims and Disputes provisions herein.

  • The District may, as provided by law, by Construction Change Directive and without invalidating the Contract, order changes in the Work consisting of additions, deletions, or other revisions.

  • These changes shall be effected by written Change Order, Construction Change Directive, or by Architect’s response(s) to RFI(s), or by Architect’s Supplemental Instructions (“ASI”).

  • A Change Order or Construction Change Directive will become effective without Developer’s signature provided District indicates it as a “Unilateral Change Order”.


More Definitions of Construction Change Directive

Construction Change Directive shall have the meaning ascribed in Paragraph 7.3 of the Trade Contract Agreement.
Construction Change Directive means a written order to Contractor, issued after execution of the Contract, signed by the District Representative and/or Architect and Contractor, authorizing a change in the Work and potentially a Change Order.
Construction Change Directive has the meaning set forth in Section 1.7.5.
Construction Change Directive has the meaning set forth in Section 16.4.
Construction Change Directive means a written order prepared by the Designer and signed by Owner, directing a change in the Work and stating a proposed basis for adjustment, if any, in the Contract Price or Contract Time, or both. Owner may, by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, or other revisions; even if it may impact the Contract Price or Contract Time.
Construction Change Directive means a written order signed by the DFCM, directing a change in the Work and stating a proposed basis for adjustment, if any, in the Contract Sum or Contract Time, or both. The DFCM may by Construction Change Directive, without
Construction Change Directive or “CCD” means a written order by the Authority to the Design-Builder directing or authorizing some change to the Design-Build Contract Documents for which there has been no determination by the Authority as to the Design-Builder’s entitlement to Compensation and/or a Design-Build Contract Time extension. If, ultimately, there is an agreement on Compensation and/or a Design-Build Contract Time extension, for a CCD, a Change Order shall be issued by the Authority to the Design- Builder resolving the CCD.