Generation Compensation in offtake constraints due to Grid Unavailability Sample Clauses

Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Solar Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECI:
AutoNDA by SimpleDocs
Generation Compensation in offtake constraints due to Grid Unavailability. Duringthe operation of the plant, shall endeavor to ensure 95% of grid availability inacontractyear,however,therecanbesomeperiodswheretheProjectcangener ate power but due to temporary transmission unavailability, the power is notevacuated, for reasons not attributable to the SPG. In such cases, subject to thesubmissionofdocumentaryevidencesfromthecompetentauthority,thegene ration compensation shall be restricted to the following and there shall be noother claim,directly orindirectly against : DurationofGridunavailability ProvisionforGenerationCompensation Grid unavailability in excess GenerationLoss=[(AverageGenerationperhour of5% in a contract year as definedin the PPA(only period during the Contract Year) × (number of hours
Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the Project, there can be some periods where the Project can generate power but due to temporary transmission unavailability the power is not evacuated, for reasons not attributable to the SPD. In such cases the generation compensation shall be addressed in following manner:
Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Solar Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted and payable by the Buying Utility(ies) as under and there shall be no other claim, directly or indirectly against SECI: Duration of Grid unavailability Provision for Generation Compensation Grid unavailability beyond 175 hours in a Contract Year (as defined in Article 1) Generation Compensation= ((Tariff X Solar Power (MW) offered but not scheduled by the Buying Entity)) X 1000 X No. of hours of grid unavailability. However, in the case of third-party sale or sale in the power exchange, as price taker, the 95% of the amount realized, after deducting expenses, shall be adjusted against the Generation compensation payable, on monthly basis. Compensation (if any) calculated as per above provision, will be paid to the SPD on an annual basis.
Generation Compensation in offtake constraints due to Grid Unavailability. During operation, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the RPD. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted and payable by the Buying Utility(ies) as under, and there shall be no claim, directly or indirectly against SECI:
Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the Project, there can be some periods where the Project can generate power but due to temporary transmission unavailability the power is not evacuated, for reasons not attributable to the WPD. In such cases the generation compensation shall be addressed in following manner: Duration of Grid unavailability Provision for Generation Compensation Grid unavailability in a contract year as beyond 50 hours in a Contract Year as defined in the PPA: Generation Loss = [(Average Generation per hour during the Contract Year) × (number of hours of grid unavailability during the Contract Year)] Where, Average Generation per hour during the Contract Year (kWh) = Total generation in the Contract Year (kWh) ÷ 8766 hours less total hours of grid unavailability in a Contract Year. The excess generation by the WPD equal to this generation loss shall be procured by the Buying Entity at the PSA tariff so as to offset this loss in the succeeding 3 (three) Contract Years. (Contract Year, shall be as defined in the PPA.)
Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Solar Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECI: Duration of Grid unavailability Provision for Generation Compensation Grid unavailability in a contract Generation Loss = [(Average year as defined in the PPA: (only Generation per hour during the period from 8 am to 6 pm to be Contract Year) × (number of hours of counted): grid unavailability during the Contract Year)] Where, Average Generation per hour T h during the Contract Year (kWh) = Total generation in the Contract Year (kWh) ÷ Total hours of generation in the Contract T Year. e excess generation by the SPD equal to this generation loss shall be procured by SECI at the PPA tariff so as to offset this loss in the succeeding 3 (three) Contract Years.
AutoNDA by SimpleDocs
Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, PGVCL shall endeavor to ensure 95% of grid availability in a contract year, however, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the SPG. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against PGVCL:
Generation Compensation in offtake constraints due to Grid Unavailability. During the operation of the plant, there can be some periods where the Project can generate power but due to temporary transmission unavailability, the power is not evacuated, for reasons not attributable to the Wind Power Developer. In such cases, subject to the submission of documentary evidences from the competent authority, the generation compensation shall be restricted to the following and there shall be no other claim, directly or indirectly against SECI: The excess generation by the WPD equal to this generation loss shall be procured at the PPA tariff so as to offset this loss in the succeeding 3 (three) Contract Years.
Generation Compensation in offtake constraints due to Grid Unavailability. Since the unavailability of the Grid is uncontrollable from MSPDCL side, the situation may be taken as a ‘Force Majeure” condition compensation towards the SPD.
Time is Money Join Law Insider Premium to draft better contracts faster.