Critical Path Sample Clauses

Critical Path. Time extensions shall depend upon the extent to which the Work on the critical path of the Construction Progress Schedule is affected, if applicable.
AutoNDA by SimpleDocs
Critical Path. The sequence of activities, events, and dependencies that determine the longest overall duration and the shortest time possible, to complete the Project. Any delay of an activity on the Critical Path directly impacts the planned Project completion date (i.e., there is no float on the Critical Path).
Critical Path. 1.9.1. The term “critical path” as used in the Contract Documents shall mean the construction activity schedule that establishes the minimum overall Project duration.
Critical Path. The critical path permits for various QF technologies are as follows: For All Non-Thermal Projects and Thermal Projects Exempt from CFC Site Certification: Geothermal: County Conditional Use Permit or Special Zone Permit Biomass: County Conditional Use Permit or Special Zone Permit, or Air Quality Permit. Wind: County Conditional Use Permit or Special Zone Permit Cogeneration: Air Quality Permit Hydro: FERC License or Exemption For Non-Exempt Thermal Projects Over 50 MW: California Energy Commission Site Certification If, for whatever reason, the permit cited above is not applicable for a project, a different necessary permit may be substituted, with the agreement of the utility involved. QF MILESTONE PROCEDURE SCHEDULE Qualifying Facility (QF): (1) provides project definition, including proof of site control; (2) requests an interconnection study; (3) pay $5/kW project fee. Utility quotes study costs, if applicable, and estimated time to complete study for QF. QF pays study cost, if applicable, for detailed study within ten days. Utility perform study. QF executes power Purchase Agreement Utility transmits interconnection study results to QFs (PPA) within six (6) within 120 days of receiving payment for study cost, and months after the QF receipt of adequate project information. provides project definition, or by the For QFs transacting with PG&E, within 45 days of receipt time QF signs the of study results, QF requests Utility to prepare a SFA, whichever date Special Facilities Agreement (SFA)1 and establishes is later. a construction start date to be used in PPA and a date QF wants Special Facilities completed. For QFs transacting with PG&E, execute the SFA within 45 days of QF receiving SFA. For QFs transacting with SCE or SDG&E, execute the IFA within 45 days of receiving the interconnection study results. Within 30 days of execution of SFA or IFA, QF provides Final Project Development Schedule to Utility with milestone dates. Notes: By QF specified date (must be within 18 months of 1 SCE calls its project definition), QF provides (1) proof of filing and agreement an acceptance of critical path permit application; and (2) Interconnection expected date of receipt of permit. Facilities Agreement IFA) and SDG&E combines its PPA and By QF specified date, (1) QF requests Utility to begin IFA into one interconnection engineering and material procurement; QF agreement. post bond or makes payment as specified in SFA or IFA, or (2) QF starts construction of it...
Critical Path a sequence of Work activities, which establish the total duration of time for the construction of the Project, and if any activity along the critical path were delayed or extended, would change the construction duration established in the approved Baseline Schedule.
Critical Path. Sequence of activities that represents the longest path through a project, which determines the shortest possible duration.
Critical Path. It is the sequence of activities that determine the maximum construction period and that are indispensable for its completion. It is presented as part of the Schedule for Execution of Works and Equipment that is incorporated into the Definitive Engineering Study. Legal Physical Sanitation Includes all those actions that are carried out on the Concession Areas, in order to regularize and formalize the property rights and real rights to such real estate, resulting in the registration of the Concession lands or real estate in the corresponding registries, which are free of charges and encumbrances that could impede the execution of the Project.
AutoNDA by SimpleDocs
Critical Path. The Developer will be responsible for initiating and diligently pursuing the Development Approval applications in accordance with the critical path schedule attached hereto as composite Exhibit D (the “Critical Path”), which Critical Path shall serve as the Developer's time frame for performance with respect to obtaining the Development Approvals and constructing the Project. Notwithstanding any other provisions of the Agreement, the dates set forth in the Critical Path shall be extended on a day for day basis for delays occasioned by the following events: acts of God; pandemic or other health related occurrence; terrorism; once construction begins - inclement weather which is in excess of those days normally forecasted by the National Weather Service for the given month in South Florida, which materially and adversely interfere with construction; unforeseen physical conditions on the site; withholding of governmental approvals or restrictions not due to the fault, delay or negligence of the Developer or the imposition of restrictions by a governmental body that materially changes the design or scope of the Project to an extent that renders the Project so difficult to construct as to make it commercially unreasonable; appeals of governmental approvals or lawsuits by any third party (whether individual or otherwise) instituted to prevent the issuance of any approvals or permits, or otherwise stop construction of the development after commencement; or similar events not reasonably foreseeable and beyond the reasonable control of Developer (collectively, “Force Majeure”). By the tenth (10th) Business Day of each month, Developer shall deliver or cause to be delivered to the CRA a list of the days during each proceeding month as to which Developer believes the Force Majeure provisions apply and the reasons therefore, together with supporting documentation as to the extension on the Critical Path. The CRA shall, within ten (10) Business Days after receipt of any such list and supporting documentation, provide notice to Developer as to whether CRA disputes that any of the days set forth on that list would give rise to an extension of time for Developer’s performance based on Force Majeure. In the event the CRA agrees with the extension requested by Developer, or any portion of the requested extension, then the Critical Path schedule shall be so extended hereunder. The CRA shall cooperate with the Developer in processing all necessary Development Approvals to be ...
Critical Path. The planned sequence of activities for a Project with a logical relationship for the elements of the Work for such Project that control the time of completion of the Work for such Project, as depicted on the Approved Construction Schedule for such Project. The Critical Path for a Project with respect to a specific Substantial Completion is the path with no Float or the least amount of Float.
Critical Path. 2.6.1 Simultaneously with the funding of the Construction Escrow Account, Tenant will provide aPhase I/II Critical Path” to the City which will set forth the projected start date of each improvement in the Phase I/II Land Based Project and the Riverboat/Floating Facility, the manner in which each improvement in the Phase I/II Land Based Project and the Riverboat/Floating Facility will be constructed and a projected completion date for each improvement in the Phase I/II Land Based Project and the Riverboat/Floating Facility.