Computation of time frames Sample Clauses

Computation of time frames. Time periods shall be calculated in calendar days, and are counted starting on the next day of the event which triggers them.
AutoNDA by SimpleDocs
Computation of time frames. Derogating to the provisions of articles 640 et seq. of the French Civil Procedure Code, and subject to the various provisions of the Contract, time periods shall be calculated in calendar days, and are counted starting on the next day of the event which triggers them.

Related to Computation of time frames

  • Computation of Time In computing any period of time prescribed or allowed by procedures herein, the date of the act, event, or default for which the designated period of time begins to run shall not be included. The last day of the period so computed shall be counted, unless it is a Saturday, a Sunday, or a legal holiday, in which event the period runs until the end of the next day which is not a Saturday, a Sunday, or a legal holiday.

  • Computation of Time Periods In this Agreement in the computation of periods of time from a specified date to a later specified date, the word “from” means “from and including” and the words “to” and “until” each mean “to but excluding”.

  • Calculation of Time Periods Unless otherwise specified, in computing any period of time described in this Agreement, the day of the act or event after which the designated period of time begins to run is not to be included and the last day of the period so computed is to be included, unless such last day is a Saturday, Sunday or legal holiday under the laws of the State in which the Property is located, in which event the period shall run until the end of the next day which is neither a Saturday, Sunday or legal holiday. The final day of any such period shall be deemed to end at 5 p.m., local time.

  • Calculation of Time For the purposes of this Agreement, “days” refers to calendar days unless otherwise specified.

  • Computation of Overtime In computing overtime a period of thirty (30) minutes or less shall be counted as one-half (½) hour and a period of more than thirty (30) minutes but less than sixty (60) minutes shall be counted as one (1) hour.

  • Extension of Time Limits The time limits referred to in this Article may be extended by mutual agreement of the parties in writing.

  • Extension of time for completion (i) Without prejudice to any other provision of this Agreement for and in respect of extension of time, the Contractor shall be entitled to extension of time in the Project Completion Schedule (the “Time Extension”) to the extent that completion of any Project Milestone is or will be delayed by any of the following, namely:

  • Calculation of Overtime If the overtime work has been carried out before as well as after the regular working hours during a certain day, the overtime periods shall be added together. Only full half hours are included in the calculation.

  • Change of Time Periods The time periods and/or dates described in this Agreement with respect to the giving of notices and hearings are subject to approval and change by the Court or by written agreement of Class Counsel and Counsel for Defendant, without notice to Settlement Class Members. The Parties reserve the right, by agreement and subject to Court approval, to grant any reasonable extension of time that might be needed to carry out any of the provisions of this Agreement.